Centrala electrică cu ciclu combinat Gissi, Gissi, Italia

33.Gas turbine 32.Measuresments 31.Erection of steam turbine 28. Erection of air intake manifold 29. Steam turbine Rotor 30.Steam turbine rotor 27. Single shaft 26.Introduction of rotor in generator's stator 25. Unloading the stator 24. Introduction of rotor in generator's stator 23.Generator 22.Stator generator erection 19.Steam turbine erection 20.Steam turbine 21 Closed steam turbine 18.Steam turbine erection
33.Gas turbine
32.Measuresments
31.Erection of steam turbine
28. Erection of air intake manifold
29. Steam turbine Rotor
30.Steam turbine rotor
27. Single shaft
26.Introduction of rotor in generator's stator
25. Unloading the stator
24. Introduction of rotor in generator's stator
23.Generator
22.Stator generator erection
19.Steam turbine erection
20.Steam turbine
21 Closed steam turbine
18.Steam turbine erection

Proiect: Centrala electrică cu ciclu combinat gaz-abur Gissi, Gissi, Italia

An:

Obiectivul lucrării: Instalarea a 2 noi grupuri de 400 MW – turbine, generatoare și instalații auxiliare

Ciclu combinat, cu un singur arbore, compus din:

  • Turbină pe gaz ALSTOM GT26-280MW
  • Turbină pe abur ALSTOM STF15C-140 MW