Project: Pumped storage hydropower plant Chaira, Bulgaria

Year: 2019 – 2022

Scope of work: Modernization of the 4 reversible Francis turbines

The modernization of the units involves:

  • Improving the efficiency by modifying the hydraulic contour of the runner
  • Stopping water leakage by modifying the wicket gates system
  • Renewing the corrosion protection
  • Replacing the cooling water system
  • Replacing the high-pressure oil unit
No. of units4
Nominal output (pump/turbine) [MW]197 / 216
Maximum discharge (turbine mode) [m³/s]36,1
Nominal net head [m]676,8
Nominal speed [rpm]600
Runner diameter [mm]3600